Lastly, we need to apply the new screen
Task Issue Type Screen Scheme
to the project:
1. Navigate to
Administration
|
Projects
.
2. Select a project from the list.
3. Select
Screens
from the left-hand side panel.
4. Navigate to
Actions
|
Use a different scheme
.
5. Select the new
Task Issue Type Screen Scheme
and click on
Associate
.