Agriculture Reference
In-Depth Information
Table 7.1 (continued)
Sr. No.
Item specifications
Unit of work
Required man-days
Unskilled
Semi-skilled
Skilled
(ii) S4
1,000 m
48
(iii) S5
1,000 m
72
(d) Terrain slope is 25 %, and soil of hardness class:
(i) S3
1,000 m
45
(ii) S4
1,000 m
60
(iii) S5
1,000 m
90
4-7
Construction of contour bunds in fields, pasture lands, etc. terrain having a slope of 1-5 %,
including excavation, formation, and hand compaction to 90 % natural density, where
(a) The bund is of standard section CB-1, and the soil is of standard hardness class:
(i) S1, S2, or S3
100 m
33
(ii) S4 or S5
100 m
59
(b) The bund is of standard section CB-2, and the soil is of standard hardness class:
(i) S1, S2, or S3
100 m
41
(ii) S4 or S5
100 m
74
(c) The bund is of standard section CB-3, and the soil is of standard hardness class:
(i) S1, S2, or S3
100 m
57
(ii) S4 or S5
100 m
102
(d) The bund is of standard section CB-4, and the soil is of standard hardness class:
(i) S1, S2, or S3
100 m
69
(ii) S4 or S5
100 m
125
(e) The bund is of standard section CB-5, and the soil is of standard hardness class:
(i) S1, S2, or S3
100 m
97
(ii) S4 or S5
100 m
174
4-8
Construction of loose-stone check dams (LSCDs), including dry-stone masonry work, laying
humus, litter, and clay on upstream surface so as to make it impervious, and pitching of
downstream ground over a distance of 5 m in 30 cm thickness, where
(a) Stones are made available in stack on site, such as those already transported by tractor, etc.
100 m 3
40
100 m 3
(b) Stones have to be collected and fetched from an average distance of 100 m
80
 
Search WWH ::




Custom Search