Civil Engineering Reference
In-Depth Information
Table B.3 ( Continued )
Activity ID Activity Name
Original
Duration
Activity
Status
Predecessors
Successors
BA911
Finish carpentry and millwork
5
Not Started BA910
BA940
BA912
Install plumbing fixtures
2
Not Started BA910
BA940
BA913
Install elevator cab and finishes
2
Not Started BA800, BA880
BA940
BA930
Paint building interior
15
Not Started BA890
BA940
BA940
Touch-up and cleanup
1
Not Started BA911, BA912,
BA913, BA930
BA941
BA941
Test and balance HVAC equipment
1
Not Started BA940
BA950
BA950
Finishes milestone
0
Not Started BA941
BA960
BA960
Punch list
2
Not Started BA950
BA970
BA970
Building addition complete
0
Not Started BA960
BA983
Relocate HVAC chiller
3
Not Started BA831
BA871
CS305
Start up and debug system
9
Not Started CS730, CS740,
CS750, CS760
CS800
Table B.4 Earned Value Report
WBS
Activity ID Activity Name
Activity
Status
Planned
Cost
(BCWS)
Actual
Cost
(ACWP)
Earned
Value
(BCWS)
Cost
Variance
Variance at
Completion
Caprini Corporation
Apex Project
Apex Construction
Office Building Addition
Design and Engineering
BA400
Design building addition Completed $5,520.00
$5,520.00 $5,520.00
$0.00
$0.00
BA469
Assemble technical
data for heat pump
Completed
$720.00
$720.00
$720.00
$0.00
$0.00
BA470
Review technical data
on heat pumps
Completed $2,400.00
$2,400.00 $2,400.00
$0.00
$0.00
BA501
Review and approve
designs
Completed
$0.00
$1,800.00
$0.00 ($1,800.00) ($1,800.00)
Subtotal
$8,640.00 $10,440.00 $8,640.00 ($1,800.00)
($1,800.00)
( continued overleaf )
 
Search WWH ::




Custom Search