Civil Engineering Reference
In-Depth Information
Table B.4 ( Continued )
WBS
Activity ID Activity Name
Activity
Status
Planned
Cost
(BCWS)
Actual
Cost
(ACWP)
Earned
Value
(BCWS)
Cost
Variance
Variance at
Completion
Foundation
BA630
Begin building
construction
Completed
$0.00
$0.00
$0.00
$0.00
$0.00
BA640
Site preparation
Completed
$3,096.00
$532.69
$3,096.00
$2,563.31
$2,563.31
BA650
excavation
Completed
$1,720.00
$14.58
$1,720.00
$1,705.42
$1,705.42
BA660
Install underground
water lines
Completed
$1,320.00
$6.11
$1,320.00
$1,313.89
$1,313.89
BA670
Install underground
electric conduit
Completed
$1,280.00
$5.93
$1,280.00
$1,274.07
$1,274.07
BA680
Form/pour concrete
footings
Completed $13,160.00
$394.95 $13,160.00 $12,765.05 $11,965.05
BA681
Concrete foundation
walls
Completed
$9,960.00
$409.33
$9,960.00
$9,550.67
$8,750.67
BA690
Form and pour slab
Completed
$5,940.00
$147.59
$5,940.00
$5,792.41
$5,392.41
BA700
Backfill and compact
walls
Completed
$728.00
$1.87
$728.00
$726.13
$726.13
BA701
Foundation phase
complete
Completed
$0.00
$0.00
$0.00
$0.00
$0.00
Subtotal
$37,204.00
$1,513.05 $37,204.00 $35,690.95 $33,690.95
Structure
BA702
Begin structural phase
Completed
$0.00
$0.00
$0.00
$0.00
$0.00
BA710
Erect structural frame
Completed $11,600.00
$470.74 $11,600.00 $11,129.26
$9,529.26
BA712
Floor decking
Completed
$8,120.00
$291.20
$8,120.00
$7,828.80
$6,708.80
BA720
Erect stairwell and
elevator walls
Completed
$1,600.00
$360.89
$1,600.00
$1,239.11
$1,239.11
BA730
Concrete first floor
Completed
$9,510.00
$1,888.80
$9,510.00
$7,621.20
$6,421.20
BA731
Concrete basement
slab
Completed $14,600.00
$3,591.36 $14,600.00 $11,008.64
$9,408.64
BA732
Structure complete
Completed
$0.00
$0.00
$0.00
$0.00
$0.00
BA735
Concrete second floor
Completed
$9,510.00
$3,957.50
$9,510.00
$5,552.50
$4,352.50
Subtotal
$54,940.00 $10,560.49 $54,940.00 $44,379.51 $37,659.51
 
Search WWH ::




Custom Search