Table B.3 List of Activities with Predecessors and Successors
Activity ID Activity Name
Original
Duration
Activity
Status
Predecessors
Successors
BA702
Begin structural phase
0
Completed
BA710
BA712
Floor decking
14
Completed
BA710
BA730
BA720
Erect stairwell and elevator walls
10
Completed
BA730
BA732, BA860
BA730
Concrete first floor
15
Completed
BA712
BA720, BA731,
BA810, BA735
BA731
Concrete basement slab
10
Completed
BA730
BA732
BA732
Structure complete
0
Completed
BA720, BA731
BA750
BA735
Concrete second floor
15
Completed
BA730
BA741
Close-in phase begins
0
Not Started BA750
BA750
Brick exterior walls
7
Not Started BA600, BA732
BA741, BA770,
BA780
BA770
Install door and window frames
1
Not Started BA750
BA790
BA780
Insulation and built-up roofing
10
Not Started BA750, BA790
BA800
BA790
Install exterior doors and windows
2
Not Started BA770
BA780, BA800
BA800
Building enclosed
0
Not Started BA780, BA790
BA830, BA831,
BA850, BA890,
BA913
BA809
Rough-in phase begins
0
Completed
BA810
BA810
Set mechanical and electrical equipment
15
Completed
BA730
BA809, BA820
BA820
Install HVAC ducts
10
Completed
BA810
BA830, BA840
BA830
Insulate ducts
2
Not Started BA800, BA820
BA831
BA831
Set heat pump
5
Not Started BA550, BA800,
BA830
BA870, BA983
BA840
Rough-in plumbing/piping
1
Not Started BA820
BA850
BA850
Install wiring and cable
15
Not Started BA800, BA840
BA870
BA860
Install elevator rails and equipment
1
Not Started BA720
BA880
BA870
Connect equipment
3
Not Started BA831, BA850
BA871
BA871
Start up and test HVAC
1
Not Started BA870, BA983
BA880
BA880
Rough-in complete
0
Not Started BA860, BA871
BA890, BA913
BA890
Drywall in offices
15
Not Started BA800, BA880
BA899, BA900,
BA930
BA899
Finishes phase begins
1
Not Started BA890
BA900
Install ceiling grid
15
Not Started BA890
BA901, BA902,
BA910
BA901
Install lighting fixtures
3
Not Started BA900
BA910
BA902
Install AC grills and registers
5
Not Started BA900
BA910
BA910
Install floor and carpeting
5
Not Started BA620, BA900,
BA901, BA902
BA911, BA912