Table B.2 (
Continued
)
Department
Activity ID
Activity Name
Orig Dur Rem Dur %
Calendar
Resp Start
Finish
AS118
Training
manuals/system
operation
7
7
0 Automated System
Calendar 1
JM
14-Feb-03
24-Feb-03
AS900
System buyoff
0
0
0 Standard 5-Day
Workweek
KL
24-Feb-03
CS311
Start conveyor
installation
0
0
0 Conveyor System
Calendar 1
JN
01-Apr-03
]
CS315
Site preparation
18
18
0 Conveyor System
Calendar 1
JN
01-Apr-03
24-Apr-03
CS700
Install conveyor 211
12
12
0 Conveyor System
Calendar 1
JN
25-Aug-03
10-Sep-03
CS770
Operation manuals
18
18
0 Conveyor System
Calendar 1
KL
25-Aug-03
18-Sep-03
CS710
Install conveyor 212
8
8
0 Conveyor System
Calendar 1
JN
10-Sep-03
22-Sep-03
CS720
Install conveyor 213
9
9
0 Conveyor System
Calendar 1
JN
22-Sep-03
03-Oct-03
CS730
Install conveyor 214
10
10
0 Conveyor System
Calendar 1
JN
03-Oct-03
17-Oct-03
CS740
Field piping
10
10
0 Conveyor System
Calendar 1
JN
07-Nov-03
20-Nov-03
CS750
Field wiring
10
10
0 Conveyor System
Calendar 1
JN
07-Nov-03
20-Nov-03
CS760
Field painting
4
4
0 Conveyor System
Calendar 1
JN
05-Dec-03
11-Dec-03
CS800
Conveyor system
complete
0
0
0 Conveyor System
Calendar 1
JN
24-Dec-03
AS103
Install robot base
14
0
100 Automated System
Calendar 1
KL
15-Aug-02 A 04-Sep-02 A
AS104
Run sealant, air, &
water piping
13
0
100 Automated System
Calendar 1
KL
15-Aug-02 A 02-Sep-02 A
AS105
Install temperature
control equipment
29
0
100 Automated System
Calendar 1
MF
20-Sep-02 A 30-Oct-02 A
AS106
Set & connect
robots
3
0
100 Automated System
Calendar 1
KL
30-Oct-02 A 05-Nov-02 A
AS219
Install system &
miscellaneous
components
19
0
100 Automated System
Calendar 1
KL
05-Nov-02 A 02-Dec-02 A
AS240
Installation begins
0
0
100 Automated System
Calendar 1
PR
15-Aug-02 A
AS310
Site preparation
3
0
100 Automated System
Calendar 1
GG
12-Aug-02 A 14-Aug-02 A
AS315
Install electrical
power
14
0
100 Automated System
Calendar 1
JM
15-Aug-02 A 04-Sep-02 A
Subtotal
357
271
12-Aug-02 A 24-Dec-03 A