Table B.2 (
Continued
)
Department
Activity ID
Activity Name
Orig Dur Rem Dur %
Calendar
Resp Start
Finish
Information Systems Department
AS110
Test & debug line B
19
5
74.17 Automated System
Calendar 1
JM
02-Dec-02 A 16-Dec-02
AS109
Test & debug line A
19
5
74.17 Automated System
Calendar 1
JM
02-Dec-02 A 16-Dec-02
AS108
Install system
controller
13
7
47.62 Automated System
Calendar 1
KL
02-Dec-02 A 18-Dec-02
AS250
Install bar rails
4
3
23.8 Automated System
Calendar 1
KL
09-Dec-02 A 13-Dec-02
AS270
Trim robot paths line
B
2
2
0 Automated System
Calendar 1
KL
13-Dec-02
16-Dec-02
AS260
Trim robot paths line
A
2
2
0 Automated System
Calendar 1
KL
13-Dec-02
16-Dec-02
AS112
Start-up line B
8
8
0 Automated System
Calendar 1
JM
17-Dec-02
26-Dec-02
AS111
Pilot start line A
2
2
0 Automated System
Calendar 1
JM
17-Dec-02
18-Dec-02
AS265
Path refinement and
shakedownline A
4
4
0 Automated System
Calendar 1
JM
19-Dec-02
24-Dec-02
AS275
Path refinement and
shakedownline B
4
4
0 Automated System
Calendar 1
JM
27-Dec-02
01-Jan-03
AS113
Install proces-
sor/software/data
tapes
3
3
0 Automated System
Calendar 1
LH
02-Jan-03
06-Jan-03
AS150
Production start
0
0
0 Automated System
Calendar 1
LH
02-Jan-03
AS114
Calibrate robot
controller & power
up
1
1
0 Automated System
Calendar 1
KL
07-Jan-03
07-Jan-03
AS115
Load system
software
1
1
0 Automated System
Calendar 1
LH
08-Jan-03
08-Jan-03
AS116
Program
14
14
0 Automated System
Calendar 1
LH
09-Jan-03
28-Jan-03
AS600
Manual operation
ready
0
0
0 Automated System
Calendar 1
LH
09-Jan-03
09-Jan-03
AS280
Test software
4
4
0 Automated System
Calendar 1
LH
29-Jan-03
03-Feb-03
AS285
Debug software
6
6
0 Automated System
Calendar 1
LH
04-Feb-03
11-Feb-03
AS117
Start-up procedure
development
2
2
0 Automated System
Calendar 1
LH
12-Feb-03
13-Feb-03
AS500
Automatic operation
ready
0
0
0 Automated System
Calendar 1
LH
12-Feb-03
12-Feb-03