Civil Engineering Reference
In-Depth Information
Table B.2 (
Continued
)
Department
Activity ID
Activity Name
Orig Dur Rem Dur %
Calendar
Resp Start
Finish
AS201
Review bids for
temperature control
equipment
5
0
100 Automated System
Calendar 1
MF
21-Aug-02 A 27-Aug-02 A
AS202
Award contract for
temperature control
equipment
0
0
100 Automated System
Calendar 1
MF
28-Aug-02 A 28-Aug-02 A
AS213
Prepare and solicit
bids for system
controller
7
0
100 Automated System
Calendar 1
KL
02-Aug-02 A 13-Aug-02 A
AS214
Review bids for
system controller
4
0
100 Automated System
Calendar 1
KL
13-Aug-02 A 19-Aug-02 A
AS215
Award contract for
system controller
1
0
100 Automated System
Calendar 1
KL
19-Aug-02 A 20-Aug-02 A
AS218
Fabricate and deliver
system controller
24
0
100 Automated System
Calendar 1
KL
20-Aug-02 A 23-Sep-02 A
AS206
Fabricate & deliver
temperature control
equipment
17
0
100 Automated System
Calendar 1
MF
28-Aug-02 A 19-Sep-02 A
Subtotal
287
49
18-Jul-02 A 25-Aug-03 A
Construction Department
BA750
Brick exterior walls
7
7
0 Standard 5-Day
Workweek
JN
24-Jan-03
03-Feb-03
BA840
Rough-in
plumbing/piping
1
1
0 Office Building
Addition Calendar 1
JN
24-Jan-03
24-Jan-03
BA860
Install elevator rails
and equipment
1
1
0 Office Building
Addition Calendar 1
JN
24-Jan-03
24-Jan-03
BA770
Install door and
window frames
1
1
0 Office Building
Addition Calendar 1
JN
31-Jan-03
31-Jan-03
BA790
Install exterior doors
and windows
2
2
0 Office Building
Addition Calendar 1
JN
03-Feb-03
04-Feb-03
BA780
Insulation and
built-up roofing
10
10
0 Office Building
Addition Calendar 1
JN
04-Feb-03
17-Feb-03
BA741
Close-in phase
begins
0
0
0 Office Building
Addition Calendar 1
JN
04-Feb-03
BA800
Building enclosed
0
0
0 Office Building
Addition Calendar 1
JN
17-Feb-03
BA850
Install wiring and
cable
15
15
0 Office Building
Addition Calendar 1
JN
18-Feb-03
10-Mar-03
BA830
Insulate ducts
2
2
0 Office Building
Addition Calendar 1
JN
18-Feb-03
19-Feb-03
(
continued overleaf
)