Table B.2 (
Continued
)
Department
Activity ID
Activity Name
Orig Dur Rem Dur %
Calendar
Resp Start
Finish
Purchasing Department
CS400
Prepare and solicit
bids for conveyors
12
12
0 Conveyor System
Calendar 1
KL
17-Jun-03
03-Jul-03
CS410
Review bids for
conveyors
2
2
0 Conveyor System
Calendar 1
KL
03-Jul-03
07-Jul-03
CS420
Award contract
1
1
0 Conveyor System
Calendar 1
KL
07-Jul-03
08-Jul-03
CS450
Fabricate and
deliver conveyors
34
34
0 Conveyor System
Calendar 1
KL
08-Jul-03
25-Aug-03
BA407
Prepare and solicit
bids for flooring
5
0
100 Office Building
Addition Calendar 1
LH
13-Aug-02 A 19-Aug-02 A
BA408
Review bids for
flooring
3
0
100 Office Building
Addition Calendar 1
LH
20-Aug-02 A 22-Aug-02 A
BA409
Award contract for
flooring
1
0
100 Office Building
Addition Calendar 1
LH
23-Aug-02 A 23-Aug-02 A
BA411
Prepare and solicit
bids for heat pump
3
0
100 Office Building
Addition Calendar 1
JN
06-Aug-02 A 08-Aug-02 A
BA412
Review bids for heat
pump
2
0
100 Office Building
Addition Calendar 1
JN
09-Aug-02 A 12-Aug-02 A
BA413
Award contract for
heat pump
1
0
100 Office Building
Addition Calendar 1
JN
13-Aug-02 A 13-Aug-02 A
BA421
Prepare and solicit
bids for brick
exterior
3
0
100 Office Building
Addition Calendar 1
JN
06-Aug-02 A 08-Aug-02 A
BA422
Review bids for brick
3
0
100 Office Building
Addition Calendar 1
JN
09-Aug-02 A 13-Aug-02 A
BA423
Award contract for
brick
1
0
100 Office Building
Addition Calendar 1
JN
14-Aug-02 A 14-Aug-02 A
BA450
Assemble brick
samples
3
0
100 Office Building
Addition Calendar 1
JN
18-Jul-02 A 22-Jul-02 A
BA480
Assemble and
submit flooring
samples
8
0
100 Office Building
Addition Calendar 1
LH
18-Jul-02 A 29-Jul-02 A
BA550
Fabricate and
deliver heat pump
and controls
88
0
100 Office Building
Addition Calendar 1
JN
14-Aug-02 A 13-Dec-02 A
BA600
Deliver brick
58
0
100 Office Building
Addition Calendar 1
JN
15-Aug-02 A 05-Nov-02 A
BA620
Fabricate and
deliver flooring
58
0
100 Office Building
Addition Calendar 1
LH
26-Aug-02 A 13-Nov-02 A
AS200
Prepare and solicit
bids for temperature
control equipment
3
0
100 Automated System
Calendar 1
MF
16-Aug-02 A 21-Aug-02 A