Civil Engineering Reference
In-Depth Information
Table B.2 Apex Project—List of Activities (an asterisk indicates a constraint on the activity)
Department
Activity ID
Activity Name
Orig Dur Rem Dur %
Calendar
Resp Start
Finish
Engineering Department
CS300
01-Apr-03
*
System design
30
30
0 Conveyor System
Calendar 1
MF
12-May-03
CS310
Review and approve
design
8
8
0 Conveyor System
Calendar 1
MF
13-May-03
22-May-03
CS430
Prepare drawings for
conveyors
10
10
0 Conveyor System
Calendar 1
MF
23-May-03
05-Jun-03
CS440
Review and approve
drawings for
conveyors
7
7
0 Conveyor System
Calendar 1
MF
06-Jun-03
17-Jun-03
BA400
Design building
addition
23
0
100 Office Building
Addition Calendar 1
GG
04-Jun-02 A 04-Jul-02 A
BA469
Assemble technical
data for heat pump
3
0
100 Office Building
Addition Calendar 1
GG
18-Jul-02 A 22-Jul-02 A
BA470
Review technical
data on heat pumps
10
0
100 Office Building
Addition Calendar 1
GG
23-Jul-02 A 05-Aug-02 A
BA501
Review and approve
designs
9
0
100 Office Building
Addition Calendar 1
GG
05-Jul-02 A 17-Jul-02 A
BA530
Review and approve
brick samples
10
0
100 Office Building
Addition Calendar 1
JN
23-Jul-02 A 05-Aug-02 A
BA560
Review and approve
flooring
10
0
100 Office Building
Addition Calendar 1
LH
30-Jul-02 A 12-Aug-02 A
AS100
Define system
requirements
14
0
100 Automated System
Calendar 1
KL
04-Jun-02 A 21-Jun-02 A
AS101
System design
30
0
100 Automated System
Calendar 1
KL
24-Jun-02 A 02-Aug-02 A
AS102
Approve system
design
5
0
100 Automated System
Calendar 1
KL
05-Aug-02 A 09-Aug-02 A
AS204
Prepare drawings for
temperature control
equipment
14
0
100 Automated System
Calendar 1
KL
22-Jul-02 A 08-Aug-02 A
AS205
Review and approve
temperature control
equipment
5
0
100 Automated System
Calendar 1
KL
09-Aug-02 A 15-Aug-02 A
AS216
Prepare drawings for
system controller
4
0
100 Automated System
Calendar 1
KL
22-Jul-02 A 25-Jul-02 A
AS217
Review and approve
system controller
5
0
100 Automated System
Calendar 1
KL
26-Jul-02 A 02-Aug-02 A
Subtotal
270
55
04-Jun-02 A 17-Jun-03 A
(
continued overleaf
)