Table B.1 (
Continued
)
Respon-
sibility
Activity ID
Activity Name
Original
Duration
Remaining
Duration
Activity %
Complete
Start
Finish
Late
Start
Late
Finish
Total
Float
Plumbing Experts
108
108
20-Sep-10
17-Feb-11 09-Sep-10 14-Mar-11 18
1060
1st floor
plumbing
rough-in
3
3
0
20-Sep-10
23-Sep-10 09-Sep-10 15-Sep-10
−
5
1120
2nd floor
plumbing
rough-in
1
1
0
02-Nov-10
03-Nov-10 03-Feb-11 03-Feb-11
57
1330
1st floor
plumbing: install
fixtures
2
2
0
28-Jan-11
01-Feb-11 03-Feb-11 04-Feb-11
4
1410
2nd floor
plumbing: install
fixtures
2
2
0
11-Feb-11
15-Feb-11 04-Feb-11 07-Feb-11
−
3
1480
Plumbing finish
2
2
0
15-Feb-11
17-Feb-11 11-Mar-11 14-Mar-11 16
Rabbit-the-Roofe
r
11
11
23-Dec-10
07-Jan-11 16-Dec-10 14-Mar-11 47
1240
Roof felt
1
1
0
23-Dec-10
27-Dec-10 16-Dec-10 16-Dec-10
−
5
1265
Roof shingles
6
6
0
27-Dec-10
07-Jan-11 03-Mar-11 14-Mar-11 43
Tile and Carpet Co., Inc.
21
21
21-Feb-11
22-Mar-11 23-Feb-11 14-Mar-11
−
5
1360
1st floor flooring
12
12
0
21-Feb-11
11-Mar-11 23-Feb-11 14-Mar-11
2
1450
2nd floor flooring
10
10
0
04-Mar-11
22-Mar-11 25-Feb-11 14-Mar-11
−
5
Windows & Doors NT
20
20
11-Jan-11
08-Feb-11 18-Feb-11 14-Mar-11 25
1220
2nd floor door &
window frames
5
5
0
11-Jan-11
18-Jan-11 18-Feb-11 24-Feb-11
26
1150
1st floor door &
window frames
5
5
0
18-Jan-11
25-Jan-11 18-Feb-11 24-Feb-11
21
1370
2nd floor: hang
doors & windows
10
10
0
18-Jan-11
01-Feb-11 25-Feb-11 14-Mar-11 26
1290
1st floor: hang
doors & windows
10
10
0
25-Jan-11
08-Feb-11 25-Feb-11 14-Mar-11 21
Zapp Electric Co.
41
41
14-Jan-11
14-Mar-11 07-Feb-11 14-Mar-11
1
1130
1st floor
electrical rough-in
4
4
0
14-Jan-11
20-Jan-11 07-Feb-11 14-Feb-11
16
1200
2nd floor
electrical rough-in
4
4
0
18-Jan-11
24-Jan-11 11-Feb-11 16-Feb-11
16
1350
1st floor
electrical finish
6
6
0
11-Feb-11
21-Feb-11 15-Feb-11 22-Feb-11
2
1430
2nd floor
electrical finish
6
6
0
23-Feb-11
03-Mar-11 17-Feb-11 24-Feb-11
−
4
1500
Electrical final
4
4
0
04-Mar-11
14-Mar-11 07-Mar-11 14-Mar-11
1
Total
169
148
02-Aug-10 A 25-Mar-11 23-Aug-10 17-Mar-11
−
5