Table B.1 ( Continued )
Respon-
sibility
Activity ID
Activity Name
Original
Duration
Remaining
Duration
Activity %
Complete
Start
Finish
Late
Start
Late
Finish
Total
Float
Wall to Wall
44
44
03-Jan-11 04-Mar-11 11-Jan-11 14-Mar-11
7
1460
Stucco & paint to
ext. walls
8
8
0
03-Jan-11 17-Jan-11 01-Mar-11 14-Mar-11
37
1300
1st floor drywall
8
8
0
18-Jan-11 28-Jan-11 11-Jan-11 20-Jan-11
5
1380
2nd floor drywall
8
8
0
28-Jan-11 11-Feb-11 21-Jan-11 01-Feb-11
5
1320
1st floor
suspended
ceiling
8
8
0
28-Jan-11 11-Feb-11 01-Feb-11 14-Feb-11
2
1340
1st floor
paint/wall
covering
10
10
0
03-Feb-11 21-Feb-11 07-Feb-11 22-Feb-11
2
1400
2nd floor
suspended
ceiling
8
8
0
11-Feb-11 23-Feb-11 02-Feb-11 15-Feb-11
5
1420
2nd floor
paint/wall
covering
11
11
0
17-Feb-11 04-Mar-11 08-Feb-11 24-Feb-11
5
Master Art Landscape
16
16
14-Oct-10 05-Nov-10 22-Feb-11 16-Mar-11 94
14-Oct-10 05-Nov-10 * 22-Feb-11 16-Mar-11
1470
Site work
15
15
0
80
Mase & Company
46
46
29-Sep-10 02-Dec-10 22-Sep-10 19-Nov-10 8
1100
1st floor internal
CMU walls
14
14
0
29-Sep-10 21-Oct-10
22-Sep-10 12-Oct-10
5
1090
1st floor external
CMU walls
10
10
0
29-Sep-10 14-Oct-10
28-Sep-10 12-Oct-10
1
1180
2nd floor internal
CMU walls
16
16
0
04-Nov-10 02-Dec-10 28-Oct-10 19-Nov-10 5
1170
2nd floor external
CMU walls
12
12
0
04-Nov-10 23-Nov-10 03-Nov-10 19-Nov-10 1
Ross Carpentry & Framing
33
33
02-Dec-10 18-Jan-11 22-Nov-10 28-Feb-11
30
1190
Roof trusses
8
8
0
02-Dec-10 16-Dec-10 22-Nov-10 06-Dec-10 5
1230
Roof sheathing
5
5
0
16-Dec-10 23-Dec-10 08-Dec-10 14-Dec-10 5
1280
Internal partition
framing
12
12
0
28-Dec-10 18-Jan-11 20-Dec-10 10-Jan-11
5
1270
Roof insulation
2
2
0
28-Dec-10 30-Dec-10 31-Jan-11 01-Feb-11
21
1260
Soffit & facia
3
3
0
28-Dec-10 03-Jan-11 24-Feb-11 28-Feb-11
37
( continued overleaf )
 