Civil Engineering Reference
In-Depth Information
Table B.2 (
Continued
)
Department
Activity ID
Activity Name
Orig Dur Rem Dur %
Calendar
Resp Start
Finish
BA831
Set heat pump
5
5
0 Office Building
Addition Calendar 1
JN
20-Feb-03 26-Feb-03
BA983
Relocate HVAC
chiller
3
3
0 Standard 5-Day
Workweek
JN
27-Feb-03 03-Mar-03
BA870
Connect equipment
3
3
0 Office Building
Addition Calendar 1
JN
11-Mar-03 13-Mar-03
BA871
Start up and test
HVAC
1
1
0 Office Building
Addition Calendar 1
JN
14-Mar-03 14-Mar-03
BA880
Rough-in complete
0
0
0 Office Building
Addition Calendar 1
JN
14-Mar-03
BA890
Drywall in offices
15
15
0 Office Building
Addition Calendar 1
LH
17-Mar-03 04-Apr-03
BA913
Install elevator cab
and finishes
2
2
0 Office Building
Addition Calendar 1
JN
17-Mar-03 18-Mar-03
BA930
Paint building
interior
15
15
0 Office Building
Addition Calendar 1
LH
26-Mar-03 15-Apr-03
BA900
Install ceiling grid
15
15
0 Office Building
Addition Calendar 1
LH
07-Apr-03
25-Apr-03
BA899
Finishes phase
begins
1
1
0 Office Building
Addition Calendar 1
LH
07-Apr-03
07-Apr-03
BA902
Install AC grills and
registers
5
5
0 Office Building
Addition Calendar 1
JN
17-Apr-03
23-Apr-03
BA901
Install lighting
fixtures
3
3
0 Office Building
Addition Calendar 1
LH
17-Apr-03
21-Apr-03
BA910
Install floor and
carpeting
5
5
0 Office Building
Addition Calendar 1
LH
28-Apr-03
02-May-03
BA911
Finish carpentry and
millwork
5
5
0 Office Building
Addition Calendar 1
LH
05-May-03 09-May-03
BA912
Install plumbing
fixtures
2
2
0 Office Building
Addition Calendar 1
LH
05-May-03 06-May-03
BA940
Touch-up and
cleanup
1
1
0 Office Building
Addition Calendar 1
LH
12-May-03 12-May-03
BA941
Test and balance
HVAC equipment
1
1
0 Office Building
Addition Calendar 1
JN
13-May-03 13-May-03
BA950
Finishes milestone
0
0
0 Office Building
Addition Calendar 1
LH
14-May-03 14-May-03
BA960
Punch list
2
2
0 Office Building
Addition Calendar 1
LH
14-May-03 15-May-03
BA970
Building addition
complete
0
0
0 Office Building
Addition Calendar 1
LH
16-May-03 16-May-03
CS305
Start up & debug
system
9
9
0 Conveyor System
Calendar 1
JN
11-Dec-03 24-Dec-03