Duration (days) IPA a
Rel. Type b Lag (days) i
Resp. c
Activity ID Activity Title
Area
1140
1st floor HVAC
ductwork\rough-in
6
1110
ACAL
1st
1150
1st floor door & window
frames
5
1090,
1100,
1280
SS
WINT
1st
1090,
1100,
1280
FF
1160
2nd floor columns
7
1110
3
GC
2nd
1170
2nd floor external CMU walls
12
1110
MASE 2nd
1180
2nd floor internal CMU walls
16
1110
2
MASE 2nd
1190
Roof trusses
8
1160,
1170,
1180
ROSS Roof
1200
2nd floor electrical rough-in
4
1170,
1180,
1280
SS
2
ZAPP
2nd
1170,
1180,
1280
FF
2
1210
2nd floor HVAC
ductwork\rough-in
6
1190
ACAL
2nd
1220
2nd floor door & window
frames
5
1170,
1180,
1280
SS
WINT
2nd
1170,
1180,
1280
FF
1230
Roof sheathing
5
1190
ROSS Roof
1240
Roof felt
1
1230
RABT Roof
Building dry-inf f
1250
1240
GC
ALL
1260
Soffit & facia
3
1250
ROSS Roof
1265
Roof shingles
6
1240
RABT Roof
1270
Roof insulation
2
1250
ROSS Roof
1280
Internal partition framing
12
1250
ROSS ALL
1290
1st floor: hang doors &
windows
10
1150,
1280
WINT
1st
1300
1st floor drywall
8
1280
WALL 1st
1310
1st floor HVAC air handler
5
1140,
1300
ACAL
1st
1320
1st floor suspended ceiling
8
1300
WALL 1st
1330
1st floor plumbing: install
fixtures
2
1060,
1300
PLMX 1st
1340
1st floor paint/wall covering
10
1320
SS
4
WALL 1st
1330
1350
1st floor electrical finish
6
1130,
1320
ZAPP
1st
1360
1st floor flooring
12
1340,
1350
TACO
1st
( continued overleaf )
 