Duration (days) IPA a
Rel. Type b Lag (days) i
Resp. c
Activity ID Activity Title
Area
1370
2nd floor: hang doors &
windows
10
1220,
1280
WINT
2nd
1380
2nd floor drywall
8
1300
WALL 2nd
1390
2nd floor HVAC air handler
5
1210,
1380
ACAL
2nd
1400
2nd floor suspended ceiling
8
1270,
1380
WALL 2nd
1410
2nd floor plumbing: install
fixtures
2
1120,
1380
PLMX 2nd
1420
2nd floor paint/wall covering
11
1400
SS
4
WALL 2nd
1410
1430
2nd floor electrical finish
6
1200,
1400
ZAPP
2nd
1440
HVAC: install equipment
1
1310,
1390
ACAL
ALL
1450
2nd floor flooring
10
1420,
1430
TACO
2nd
1460
Stucco & paint to ext. walls
8
1260
WALL ALL
Site work g
1470
15
1020,
1090
MART ALL
1480
Plumbing finish
2
1330,
1410
PLMX ALL
1490
HVAC thermostat & test
1
1350,
1430,
1440
ACAL
ALL
1500
Electrical final
4
1340,
1350,
1420,
1430
ZAPP
ALL
1510
Building cleanup
2
1265,
1290,
1360,
1370,
1450,
1460,
1480,
1490,
1500
GC
ALL
Final check/CO h
1520
1
1470,
1510
GC
ALL
a Immediately preceding activity.
b Relationship type: SS, start to start; FF, finish to finish. If blank, the relationship is FS, finish to start.
c Responsibility.
d Notice to proceed. Make this activity a start milestone.
e The negative lag means 2nd-floor plumbing rough-in must finish 1 day before completion of the 2nd-floor slab. Note
also that the start of this activity lags 1 day behind the start of the slab activity. This makes the plumbing activity
completely contained within the slab activity.
f fMake this activity a finish milestone.
g Insert a constraint so that site work will not finish umtil about 1 week before the end of the entire project.
h Certiicate of occupancy.
i If blank, then the lag is zero.
 