that the delay disrupted the resource allocation plan, even though it affected
a noncritical activity and did not delay the entire project (see Figures 13.5
to 13.7).
Noncritical Resource Plan as Impacted
1 2345678 9 10 11 12 13 14 15 16 17 18 19 20 21 22
23 Days
A
5
B
D
G
DELAY->
E
C
F
Critical
Noncritical
Figure 13.4 Bar chart with impact of owner's delay to activity E. The owner's delay has
disrupted the planned use of the noncritical resources. While the contractor would
claim 3 days (14-16) of idle time plus 3 days (20-22) of extra crew time, a
resequencing of the noncritical resource, if possible, would mitigate the owner's delay.
As Adjusted
Noncritical Resource Plan Resequenced due to Delay
12345678 9 10 11 12 13 14 15 16 17 18 19 20 21 22
23 Days
A
B
D
G
5
E
DELAY->
C
F
Critical
No n cri t ical
Figure 13.5 With the impact of owner's delay to activity E but mitigated by
resequencing activities E and F