Civil Engineering Reference
In-Depth Information
Nonresource-constrained Mathematical Analysis
1 2345 678 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Days
A
5
B
D
G
f
f
f
E
C
F
f
f
f
f
f
f
f
f
Critical
Legend
Network dependency
Noncritical
f
f
f
f
Flo a t
Figure 13.2 Bar chart with sequence dependencies
As Planned
Noncritical Resource Plan for Better Utilization
12345 678 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Days
A
5
B
D
G
E
C
f
f
F
Critical
Network dependency
Resource constraint
Re s our c e P la n
Figure 13.3 Bar chart with resource constraints
3days. 24 The answer to this argument generally lies in the contract agree-
ment. If the contractor granted the owner ownership of the float, the owner
can use the float to absorb any delay. If the contractor has ownership of float,
he may be entitled to a time extension or compensation if he or she can prove
24 Additional compensation and/or a time extension may be involved, because even with 3 days' time
extension, the contractor still needs to hire the crew for an extra 3 days (days 8 through 25 instead of 8
through 22), unless the crew can do other work during the delay time (i.e., during days 14, 15, 1nd 16). The
alternative is to hire a second crew and do E and F concurrently (finish them both by the end of day 22).
Search WWH ::




Custom Search