Letter 177
To architect, applying for payment of expense (d)
This letter is only suitable for use with GC/Works/1 (1998).
Dear
We hereby give notice under clause 46(3)(a) of the conditions of contract as
follows:
The regular progress of the Works has been/is likely to be [ delete as appropriate ]
disrupted/prolonged [ delete as appropriate ] due to [ describe ]. In consequence of
such disruption/prolongation [ delete as appropriate ] we have properly and
directly incurred/we will properly and directly incur [ delete as appropriate ]
expense in performing the contract which we would not otherwise have
incurred and which is beyond that otherwise provided for in or reasonably to
be contemplated by the contract. We are/we expect to be [ delete as appropriate ]
entitled to an increase in the contract sum under clause 46(1).
Yours faithfully