Letter 158
To architect, providing further particulars for extension of time (a)
This letter is not suitable for use with MW, MWD or GC/Works/1
(1998).
Dear
We refer to our letter of the [ insert date ] in which we notified you of a delay
in progress of the Works likely to result in a delay to completion of the Works.
We note below particulars of the expected effects and the estimated extent of
delay in completion of the Works in respect of each relevant event specified in
our notice:
[ List relevant events separately, giving an assessment of the delay to completion in
each case together with any other supporting information. ]
We believe that you now have sufficient information to enable you to grant a
fair and reasonable extension of time.
Yours faithfully