Letter 159
To architect, providing further particulars for extension of time (b)
This letter is only suitable for use with MW, MWD or GC/Works/1
(1998).
Dear
We refer to our notice of the [ insert date ] in which we informed you of a delay
in progress of the Works likely to result in a delay to completion of the Works.
We estimate that completion will be delayed by [ insert number ] weeks and we
consider that we should be granted an extension of time for that period. We
arrive at this conclusion as follows:
[ State reasons in full and include all supporting information .]
We believe that you now have sufficient information to enable you to grant a
fair and reasonable extension of time and we look forward to hearing from
you shortly.
Yours faithfully