Letter 157
To architect, if delay occurs giving grounds for extension of time (b)
This letter is only suitable for use with MW, MWD or GC/Works/1
(1998).
Dear
It is apparent that the Works will not be complete by the date for completion.
[
Then either:
]
The circumstances are [
state
]. We estimate the delay to total [
insert period
]. We
consider that we are entitled to an extension of [
insert period
] and we will
furnish further particulars within the next few days.
[
Or:
]
The circumstances are [
state
]. We are unable to estimate the total delay at this
stage because it is continuing. When the delay is over, we will submit the
required estimate and other details immediately.
[
Then:
]
You may be assured that we are using our best endeavours to prevent delay in
progress and completion of the Works.
This notice is issued in accordance with clause 2.7 [
substitute '2.8' when using
MWD or '36(1)' when using GC/Works/1
] of the conditions of contract.
Yours faithfully