Letter 156
To architect, if delay occurs giving grounds for extension of time (a)
This letter is not suitable for use with MW, MWD or GC/Works/1
(1998).
Dear
The progress of the Works is being delayed due to [ state reasons ]. We consider
this to be a relevant event under clause [ insert number ].
The delay began on [ insert date ]. When it is finished, we will furnish you with
our estimate of delay in the completion of the Works and further supporting
particulars.
You may be assured that we are using our best endeavours to prevent delay in
progress and completion of the Works.
This notice is issued in accordance with clause 2.27.1 [ substitute '2.19.1' when
using IC or ICD or '2.24.1' when using DB ].
Yours faithfully