Letter 152
To architect, if final certificate not issued on the due date (b)
This letter is only suitable for use with IC or ICD.
Special delivery
Dear
Clause 4.14.1 of the conditions of contract requires you to issue the final
certificate within 28 days of the latest of the following events:
1.
The sending to us of the computations of the adjusted contract sum, which
we received on the [ insert date ].
2.
Your certificate of making good under clause 2.31 - [ insert date ].
Therefore, the final certificate should have been issued on the [ insert date
calculated as above ]. Some [ insert number ] weeks have passed since that date and
we have received no such certificate. You are in breach of contract, a breach for
which, we are advised, the employer will become liable after receipt of this
notification. Without prejudice to our rights in this matter, if the final certificate
is in our hands by [ insert date ], we will take no further action on such breach.
Yours faithfully
Copy: Employer