Letter 153
To architect, if final certificate not issued on the due date (c)
This letter is only suitable for use with MW or MWD.
Special delivery
Dear
Clause 4.8.1 of the conditions of contract requires you to issue the final
certificate within 28 days of receipt by you of all documentation reasonably
required for computation of the amount to be certified, provided that you have
issued your certificate under clause 2.11 [ substitute '2.12' when using MWD ].
You confirmed that all such documents were in your possession by your letter
of the [ insert date ]. You issued a clause 2.11 [ substitute '2.12' when using MWD ]
certificate on the [ insert date ].
Therefore, the final certificate should have been issued on the [ insert date
calculated as above ]. Some [ insert number ] weeks have passed since that date and
we have received no such certificate. You are in breach of contract, a breach for
which, we are advised, the employer will become liable after receipt of this
notification. Without prejudice to our rights in this matter, if the final certificate
is in our hands by [ insert date ], we will take no further action on such breach.
Yours faithfully
Copy: Employer