Letter 144
To employer, if payment in full has not been made within 7 days
despite notice of suspension
Dear
Further to our letter dated [ insert date ] stating that if payment in full was
not made within 7 days from the date of its receipt we would suspend our
obligations, we have not received any/full [ delete as appropriate ] payment.
This is to inform you that, with immediate effect, we are suspending all
our obligations under the contract.
We have left the site safe, but it is now for you to arrange security and
insurance if you persist in withholding payment.
Yours faithfully