Letter 101
To quantity surveyor, submitting a Schedule 2 quotation
This letter is only suitable for use with SBC.
Dear
Under the provisions of Schedule 2, paragraph 1.2 and in compliance with
architect's instruction number [ insert number ] dated [ insert date ], we enclose
our quotation. The quotation comprises the required adjustment to the
contract sum with calculations, the required adjustment to the time for
completion of the Works, the amount of loss and/or expense required in lieu
of any adjustment under clause 4.23 and the cost of preparing the quotation.
[ If the instruction specifically requires it, add: ]
Indicative information is included about the extra resources needed and the
method of carrying out the work.
[ Then add: ]
The quotation is open for acceptance for 7 days from the date of receipt.
Yours faithfully