Letter 102
To architect, regarding verification of vouchers for daywork
This letter is not suitable for use with MW, MWD or GC/Works/1
(1998).
Dear
We enclose vouchers numbers [ insert numbers ] in respect of [ insert description of
work ]. We should be pleased if you would verify them as required by clause 5.7
[ substitute '5.4' when using IC or ICD or '5.5' when using DB ] of the conditions of
contract.
[ If appropriate, add: ]
The clerk of works always asks to see such vouchers and it occurred to us
that it would save time if you notified us that the clerk of works was your
authorised representative for the purpose of clause 5.7 [ substitute '5.4' when
using IC or ICD or '5.5' when using DB ]. The clerk of works could officially
verify the vouchers as required by the contract. We should be interested to
hear whether this suggestion meets with your approval.
Yours faithfully