Letter 90
To architect, if a change in statutory requirements after base date
This letter is not suitable for use with IC, MW, MWD or GC/Works/1
(1998).
Dear
On [
insert date
] there was a change in statutory requirements which
necessitates an alteration or modification to the Contractor's Designed
Portion [
substitute 'to the Works' when using DB
][
give details
].
We are putting the necessary amendment in hand and we will write to you
again as soon as we are in a position to value the amendment which is to be
treated as a variation [
substitute 'change' when using DB
] instruction under the
provisions of clause 2.17.2.1 [
substitute '2.15.2.1' when using ICD or DB
]ofthe
conditions of contract. [
When using DB, add:
] In our view, this is not an
instruction to be dealt with under supplemental provision 4.
[
Then add:
]
Therefore, please take this letter as notice of delay under clause 2.27.1
[
substitute '2.19.1' when using ICD or '2.24.1' when using DB
] and application for
loss and/or expense under clause 4.23 [
substitute '4.17' when using ICD or '4.19'
when using DB
].
Yours faithfully