Letter 89
To architect, if emergency compliance with statutory
requirements required
This letter is not suitable for use with MW, MWD or
GC/Works/1 (1998).
Dear
We hereby give notice as required by clause 2.18.2 [ substitute '2.16.2' when
using IC, ICD or DB ] of the conditions of contract that we have been obliged
to carry out work constituting emergency compliance with statutory
requirements. The emergency and the steps we are taking/have taken
[ delete as appropriate ] are as follows:
[ Insert details .]
We confirm that the work carried out and materials supplied rank as a
variation [ substitute 'change' when using DB ] and we should be pleased to
receive any further instructions necessary.
Please take this letter as a notice of delay under clause 2.27.1 [ substitute '2.19.1'
when using IC or ICD or '2.24.1' when using DB ] and an application for loss
and/or expense under clause 4.23 [ substitute '4.17' when using IC or ICD or
'4.19' when using DB ].
Yours faithfully