Geoscience Reference
In-Depth Information
Construction costs
85% to 95% of total capital project costs.
Design costs
5% to 10% of total capital costs.
Geotechnical costs
0.1% to 4% of total capital costs.
Each peaks at different phase as shown in Figure 1.1.
Figure 1.1 Steps in effective use of geotechnical input throughout all phases of the project.
1.3 Relevance of scale
At each stage of the project, a different scale effect applies to the investigation.
Table 1.3 Relevance of scale.
Size study
Typical scale
Typical phase of project
Relevance
Regional
1: 100,000
Regional studies
GIS analysis/Hazard assessment
Medium
1: 25,000
Feasibility studies
Land units/Hazard analysis
Large
1: 10,000
Planning /IAS
Terrain/Risk assessment
Detailed
1: 2,000
Detailed design
Detailed development.
Risk analysis
GIS - Geographic Information Systems
1.4 Planning of site investigation
The SI depends on the phase of the project.
The testing intensity should reflect the map scale of the current phase of the study.
 
 
Search WWH ::