Geoscience Reference
In-Depth Information
1.2 Geotechnical requirements for the different
project phases
The geotechnical study involves phasing of the study to get the maximum
benefit. The benefits (
20% per phase) are approximately evenly distributed
throughout the lifecycle of the project.
Traditionally (currently in most projects), most of the geotechnical effort (
>
90%)
and costs are in the investigation and construction phases.
The detailed investigation may make some of the preliminary investigation data
redundant. Iteration is also part of optimisation of geotechnical investigations.
The geotechnical input at any stage has a different type of benefit. The Quality
Assurance (QA) benefit during construction, is as important as optimising the
location of the development correctly in the desktop study. The volume of testing
as part of QA, may be significant and has not been included in the Table. The
Table considers the Monitoring/Instrumentation as the engineering input and not
the testing (QA) input.
The observational approach during construction may allow reduced factors of
safety to be applied and so reduce the overall project costs. That approach may
also be required near critical areas without any reduction in factors of safety.
Table 1.2 Geotechnical requirements.
Geotechnical
Key Model
Relative (100% total)
Key data
Comments
Study
Effort
Benefit
Desktop
Geological
<
5%
20%
Geological setting,
Minor SI costs
study
model
existing data,
(site reconnaissance)
site history,
with significant
aerial photographs
planning benefits.
and terrain
assessment.
Definition
5%
20%
Justify investigation
Safety plans and
<
of needs
requirements and
services checks.
anticipated costs.
Physical, environmental
and allowable
site access.
Preliminary
Geological and
15%
20%
Depth, thickness
Planning/Preliminary
investigation
geotechnical
and composition
Investigation of
model
of soils and
20% of planned
strata.
detailed site
investigation.
Detailed site
Geotechnical
75%
20%
Quantitative, and
Laboratory analysis of
investigation
model
characterisation of
20% of detailed
critical or founding
soil profile.
strata.
Monitoring/
10%
20%
Instrumentation
Confirms models
<
Inspection
as required.
adopted or
QA testing.
requirements to adjust
assumptions. Increased
effort for observational
design approach.
 
 
Search WWH ::




Custom Search