FIGURE 14-3. Now restored, more than forty volunteer palm trees were damaging the historic Spring
House. Removal of these palm trees was a project requirement placed by the County Parks Department.
San Diego, California. (Photo by Mary F. Platter-Rieger.)
The landscape architect prepared the project plans and bid package in consultation with the
Caltrans biologist. The Caltrans construction division provided the contract administration for the
project installation, and the project was installed by a contractor. The documents prepared and
major events for this project are listed here:
1. Site analysis, March 1991
2. Conceptual design, April 1991
3. Project plans, June 1991
4. Begin construction, September 1991
5. Plantings and seeding installed, January 1992
6. Installation of remaining features complete, May 1992
7. Streambed agreement for California Fish and Game, compilation November 1994
8. Annual monitoring reports, October 1992-1994
9. Complete plant establishment, May 1995
10. Remove all aboveground project features, July 1995
11. Project closeout, November 1995