Snapshot four - storage of blockwork
Problem areas with five speculative houses to be constructed with labour-only sub-
contract gangs.
Complete lack of site prepara-
tion prior to the delivery of site
materials - blocks delivered and
placed on uneven ground (on
pallets)
Block stacks inadequately
banded - as the bands are
removed the blocks are allowed
to fall over
The subcontractor cannot be held
fully responsible as a prepared
area for storage of materials
was not provided by the specu-
lative contractor.