departments contain a number of pre-tender planners (dealing with programmes
for tenders). Contract planners tend to be located on major large projects and have
often been involved in the project since the tender stage.
1.10 The project surveyor
This person is one who has held a similar position on a previous contract. They must
be familiar with all aspects of surveying from the tender stage through to the
settlement of the final account. Their direct supervisor is the regional commercial
manager to whom they are directly responsible, and they are also responsible for
reporting directly to the project manager.
Knowledge requirements
To understand the company's tender, pre-contract and contractual process regard-
ing the appointment of subcontractors and work packages
To understand the valuation and payment process regarding package contractors
and domestic subcontractors
To be familiar with the company's cost/value reporting process to senior
management
To understand the monthly valuation process
To be conversant with the form of contract in respect of payment and dispute
resolution
To be familiar with work package subcontractor procedures
To be familiar with the preparation of dates to subcontractors for an extension of time
Management skills
To delegate to, and control, the site surveying team
To co-ordinate with the procurement managers regarding work package contrac-
tors and domestic subcontractors
To provide cost advice to estimators and managers at the tender preparation stage
To manage the cost/value reconciliation (CVR) process on site
To report to the project manager and commercial manager on the cost/value posi-
tion at the end of each month
To assist in the training programme of their assistant surveyor
To prepare monthly valuations and manage payments to work package
subcontractors
1.11 The procurement manager
The procurement manager may fall under the direction of the project surveyor due
to the latter's direct link with the work package subcontractors. As an alternative
they may report direct to the project manager.