Roof construction
Week number
Operations
1
234567891011121314
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
Days
Day
2 5
Original programme
Erect trusses
Roof coverings
25
Day
40
35
Day
15
Accel, programme
Area one
Position safety deck
Fix wall plates
Fix trusses/bracing
Facia/eaves
2
2
5
3
Area two
Position safety deck
Fix wall plates
Fix trusses
Facia/eaves
2
2
5
3
Area three
Position safety deck
Fix wall plates
Fix trusses
Facia/eaves
Carpentry
w ork
completed
day 21
Day
35
2
2
5
3
Time
saving
5 days
Day
10
Roof coverings
25
Project
Chinley school
Accelerated programme
Time saving 16 days
Roof construction
Short term programme
Bar chart - roof construction to Areas 1, 2 and 3
11.13 Extracts from contract programme
The company use standardised planning procedures on all major projects. The plan-
ning department support all planning stages from tender to project completion.
Planning engineers may be site based on larger projects or simply visit the site at
regular weekly/monthly intervals to upgrade the contract programme. Programmes
will initially be upgraded prior to monthly site meetings and a progress report pre-
pared with the site manager.
The company policy is to present all programmes using linked bar-chart principles
based on the Asta Development Software/Power Project.
The following programmes have been illustrated for the Chinley School Project:
Extract from retaining wall programme.
Extract from internal finishes programme.
Extract from procurement programme.
The software used for project planning is Asta Developments - Power Project / Team
Plan suite of programmes. The managers are familiar with the use and application of
Power Project and are capable of producing site short term programmes for any
stage of work.
 