The sequence of work in each area involves the following operations:
Position Safety Deck (scaffolding operation)
Fix wall plates
Unload truss and fix trusses and bracing
Work to facia and roof vents
Roof finishes (tiling) - subcontractor.
Roof to residential block
Sequence of work:
Safety Deck system in position 900 mm
below the underside of the trusses
Alternative Safety Deck system
Position Safety Deck on tubular support
under roof trusses in Area One to allow
access for fixing.
Fix timber wall plates to external wall
perimeter.
Delivery and unloading of 10 m span roof
trusses.
Position trusses on roof and temporary
strap in vertical position.
225 mm x 75mm Softwood timber wall
plates bolted to steelwork or fixed to top
of brickwork
Unloading and lifting of 10 m span
trusses into position
Trusses positioned in Area One