Table 7.1 (continued)
Sr. No.
Item specifications
Unit of work
Required man-days
Unskilled
Semi-skilled
Skilled
(a) Post being of standard size RCP-1 (0.0344 m 3 )
100 nos.
24
3
(b) Post being of standard size RCP-2 (0.0445 m 3 )
100 nos.
30
3
(c) Post being of standard size RCP-3 (0.0535 m 3 )
100 nos.
36
3
3-12
Loading or unloading of cement concrete blocks, with embedded angle-iron posts, onto a
vehicle, where:
(a) Vehicle height is less than 1.20 m, such as a bullock cart, and blocks are of size:
(i) CCB-1
1,000 nos.
3
(ii) CCB-2
1,000 nos.
6
(b) Vehicle height is more than 1.20 m, such as a truck, etc., and blocks are of size:
(i) CCB-1
1,000 nos.
5
(ii) CCB-2
1,000 nos.
9
3-13
Loading or unloading of precast cement concrete fence posts onto a vehicle, where
(a) Vehicle height is less than 1.20 m, such as a bullock cart, and fence posts are of size:
(i) RCP-1
1,000 nos.
7
(ii) RCP-2
1,000 nos.
10
(iii) RCP-3
1,000 nos.
12
(b) Vehicle height is more than 1.20 m, such as a truck, etc., and fence posts are of size:
(i) RCP-1
1,000 nos.
8
(ii) RCP-2
1,000 nos.
12
(iii) RCP-3
1,000 nos.
15
3-14
Fixing of block with angle-iron post in ground, including digging of pit, local transportation
up to a lead of 100 m manually, positioning, sinking, and refilling and compaction of soil
100 nos.
8
3-15
Fixing of angle-iron post without precast block, in pits of size 30
40 cm, including
digging of pit, preparation of concrete mix, and ramming the mix hard into the pit to secure
the post, materials being locally available or made available:
(a) In lime concrete
×
30
×
100 nos.
20
(b) In mud concrete
100 nos.
15
(c) In cement concrete, including curing for 7 days
100 nos.
25
 