Solution
The solution also requires two dummies
,see
Figure 3.5.
Figure 3.5 Solution for example 3.5
Example 3.6
Draw the arrow network for the project given next.
Activity
IPA
A
-
B
-
C
-
D
A
E
A, B
F
A, B, C
Solution
Again, the solution also requires two dummies as in Figure 3.6.
Figure 3.6 Solution for example 3.6