Example 3.4
Draw the arrow network for the project given next.
Activity
IPA
A
-
B
A
C
A
D
B
E
B, C
F
C
Solution
The solution requires two dummy activities (or simply
dummies
) (Figure 3.4).
Figure 3.4 Solution for example 3.4
From the previous examples, we can define a dummy activity as a fictitious activity
inserted in an arrow network to maintain proper logic or to distinguish the activ-
ities' identities. Two more examples demonstrate the need for dummy activities to
straighten up the logic.
Example 3.5
Draw the arrow network for the project given next.
Activity
IPA
A
-
B
-
C
-
D
A, B
E
B, C