Civil Engineering Reference
In-Depth Information
Duration (days)
Cost $
Activity ID
Activity Title
Normal
Crash
Normal
Crash
1280
Internal partition framing
12
9
4,500
5,300
1290
1st floor: hang doors & windows
10
5
5,200
6,100
1300
1st floor drywall
8
6
6,500
6,900
1310
1st floor HVAC air handler
5
3
4,000
4,400
1320
1st floor suspended ceiling
8
5
7,500
8,000
1330
1st floor plumbing: install fixtures
2
2
7,500
7,500
1340
1st floor paint/wall covering
10
6
5,700
6,300
1350
1st floor electrical finish
6
4
15,000
15,800
1360
1st floor flooring
12
8
11,000
12,000
1370
2nd floor: hang doors & windows
10
5
4,200
4,800
1380
2nd floor drywall
8
6
7,000
7,600
1390
2nd floor HVAC air handler
5
3
4,000
4,400
1400
2nd floor suspended ceiling
8
5
7,500
8,000
1410
2nd floor plumbing: install fixtures
2
2
7,500
7,500
1420
2nd floor paint/wall covering
11
7
5,400
6,000
1430
2nd floor electrical finish
6
4
17,000
17,400
1440
HVAC: Install equipment
1
1
22,000
22,000
1450
2nd floor flooring
10
7
8,500
9,100
1460
Stucco & paint to exterior walls
8
6
7,000
7, 800
1470
Site work
15
11
30,000
32,000
1480
Plumbing finish
2
2
4,500
4,500
1490
HVAC thermostat & test
1
1
5,000
5,000
1500
Electrical final
4
3
9,500
9,700
1510
Building cleanup
2
1
1,000
1,400
1520
Final check/CO
1
1
400
400
3. Accelerate the project by 2 days; you may have to do so 1 day at a time.
Record the total cost. When compressing an activity, reflect the increase in
its direct cost as an extra cost (acceleration cost) in its budget in the schedul-
ingprogram.YoumayhavetocreateanExcelspreadsheettocalculatethe
total cost.
4. Accelerate the project by an additional 2 days. Record the total cost.
5. Accelerate the project 1 extra day at a time. Determine the least cost and
least-cost duration. Print a tabular report and a bar chart displaying all activities,
along with their durations, organized by Responsibility.
6. Keep accelerating the project until it is completely crashed. Determine the crash
duration and the associated crash cost.
7. On a separate page, record the following:
a. Normal duration (number of days and date) and normal cost
b. Least-cost duration and least cost
c. Crash duration and crash cost
 
Search WWH ::




Custom Search