SCHEDULE COMPRESSION
Assignment 6
Assume the cost of overhead for the project is $500 per day. This cost is not included
in the following table, so it must be added manually after you calculate the project
duration. Do the following:
1. Make a copy of the Tampa Office Building-01 project. Call it “Tampa Office
Building-06.”
2. Enter the normal cost for each activity as shown in the following table. Calcu-
late the total cost (with normal duration).
Note : Some of this assignment will force a splitting of some activities (i.e.,
an interruption and resumption at a later date). In most cases, you must do
this manually.
Duration (days)
Cost $
Activity ID
Activity Title
Normal
Crash
Normal
Crash
1000
NTP
-
-
-
-
1010
Mobilization
3
2
4,000
5,000
1020
Clear & grub
12
6
12,000
16,000
1030
Excavation
7
5
14,000
17,020
1040
Foundation
15
11
22,000
30,000
1050
Fill, compact, and treat soil
3
2
4,000
4,500
1060
1st floor plumbing rough-in
3
2
2,500
2,800
1070
SOG
4
3
10,000
11,000
1080
1st floor columns
7
5
7,000
7,800
1090
1st floor external CMU walls
10
6
9,200
11,800
1100
1st floor internal CMU walls
14
8
7,800
9,200
1110
2nd floor suspended slab
8
6
12,000
13,600
1120
2nd floor plumbing rough-in
3
2
2,500
2,800
1130
1st floor electrical rough-in
4
2
6,000
7,400
1140
1st floor HVAC ductwork\rough-in
6
4
7,000
7,500
1150
1st floor door & window frames
5
3
3,500
4,100
1160
2nd floor columns
7
5
7,000
7,800
1170
2nd floor external CUM walls
12
7
11,500
13,300
1180
2nd floor internal CMU walls
16
9
8,500
10,100
1190
Roof trusses
8
6
10,000
11,000
1200
2nd floor electrical rough-in
4
3
6,000
6,200
1210
2nd floor HVAC ductwork\rough-in
6
4
7,000
7,500
1220
2nd floor door & window frames
5
3
2,600
3,000
1230
Roof sheathing
5
3
3,500
4,100
1240
Roof felt
1
1
400
400
1260
Soffit & facia
3
2
2,500
3,000
1265
Roof shingles
6
4
8,000
10,000
1270
Roof insulation
2
1
4,000
4,200
( continued overleaf )
 
 