Civil Engineering Reference
In-Depth Information
CHANGE ORDER
The owner issued a change order to add a vault. The vault will be built on the first
floor but will require a thickened SOG and concrete walls. The additional work will
include the following new and modified activities.
Activity ID
Activity Title
Duration (days)
IPA
Rel. Type
Lag (days)
Resp.
1070
SOG
5
1060
GC
1080
1st floor columns
7
1050
GC
1085
FRP vault walls
6
1070
GC
1080
FF
GC
1087
Vault door
2
1085
WINT
1110
2nd floor suspended slab
8
1080,
1085,
1090,
1100
GC
1300
1st floor drywall
8
1087,
1280
WALL
In addition to the preceding information, the following table provides resources
and cost for new and affected activities.
Resources
Activity ID
Activity Title
Laborer
Foreman
Carpenter
Excavator
Cost
1070
SOG
2
1
1
-
$2,000
1080
1st floor columns
2
1
1
-
$900
1085
FRP Vault walls
2
1
1
-
$800
1087
Vault door
-
-
-
-
$3,000
1110
2nd floor suspended slab
2
1
2
-
$3,000
1300
1st floor drywall
$7,000
Assignment 4
Do the following:
1. Make a copy of the Tampa Office Building-01 project. Call it “Tampa Office
Building-04.”
2. Add the new activities listed in the previous table and make any needed adjust-
ments to existing activities.
 
 
Search WWH ::




Custom Search