COST LOADING
In this exercise, the GC is cost loading the schedule but will follow two approaches.
For self-performed activities, the GC will resource load them (i.e., assign the proper
amount of labor and equipment, plus add the cost of materials, if any). 4 For sub-
contracted activities, the GC will add only the cost of these activities (no resource
loading).
Resources a
Cost b
Activity ID Activity Title
Laborer Forman Carpenter
Excavator
1000
NTP
$0
1010
Mobilization
3
1
1
$2,000
1020
Clear & grub
4
1
2
$0
1030
Excavation
3
1
1
$0
1040
Foundation
3
1
2
1
$5,000
1050
Fill, compact, and treat soil
2
1
1
$1,000
1060
1st floor plumbing rough-in
$2,500
1070
SOG
2
1
1
$1,500
1080
1st floor columns
2
1
2
$1,200
1090
1st floor external CMU walls
$9,200
1100
1st floor internal CMU walls
$7,800
1110
2nd floor suspended slab
2
1
2
$3,000
1120
2nd floor plumbing rough-in
$2,500
1130
1st floor electrical rough-in
$6,000
1140
1st floor HVAC ductwork\rough-in
$7,000
1150
1st floor Door & Window Frames
$3,500
1160
2nd floor columns
2
1
1
$1,200
1165
Roof shingles
$8,000
1170
2nd floor external CMU walls
$11,500
1180
2nd floor internal CMU walls
$8,500
1190
Roof trusses
$10,000
1200
2nd floor electrical rough-in
$6,000
1210
2nd floor HVAC ductwork\rough-in
$7,000
1220
2nd floor door & window frames
$2,600
1230
Roof sheathing
$3,500
1240
Roof felt
$400
1250
Building dry-in
$0
1260
Soffit & facia
$2,500
1270
Roof insulation
$4,000
1280
Internal partition framing
$4,500
4 In some computer-scheduling programs, this must also be achieved by adding a resource called lump sum ,
which is used for cash amounts only.
 
 