Cycle 0 (before crashing)
Path a
Duration (days)
ABEH
24
ACEH
25
ACFH
23
ACFG
24
ADG
23
a When the letter representing an activity is crossed, e.g., F, it
means this activity cannot be crashed (such as activity F) or has
reached its minimum/crash duration
Let us prepare the time-cost trade-off calculation table (Figure 8.12). We
have to start with the critical (longest) path: ACEH. We choose activity C
because it costs the least to crash, $40 per day. We cut the duration of C
from 8 days to 7. This action affects three paths: Cycle 1
Figure 8.12 Time-cost trade-off calculation table for example 8.1
Cycle 1
Path
Duration (days)
ABEH
24
24
ACEH
25
24
ACFH
23
22
AC FG
24
23
ADG
23
23
 