Example 8.1
Calculate the normal, least-cost, and crash durations for the following project.
Calculate the cost associated with each duration. Indirect (overhead) costs
are $120 per day.
Duration (days)
Cost ($)
Activity
IPA
Normal
Crash
Normal
Crash
A
-
5
4
500
600
B
A
7
5
350
500
C
A
8
5
800
920
D
A
11
7
1,200
1,400
E
B, C
6
4
600
700
F
C
4
4
500
500
G
D, F
7
5
700
1,000
H
E, F
6
5
300
420
Solution
This simple project has five paths (see Figure 8.11). They are listed next, along
with their lengths in days:
5,12
19,25
13,19
B
7
E
6
H
6
6,13
19,25
13,19
25
0,5
5,13
A
5
C
8
PF
25
0.5
5,13
13,17
17,24
F
4
G
7
14,18
18,25
5,16
D
11
7,18
Figure 8.11 Precedence network for project in example 8.1—PF, project finish