Civil Engineering Reference
In-Depth Information
one of two choices: “As Planned” or “Schedule Change.” If the project
manager chooses the first, no further paperwork is needed for that project.
The scheduler assumes that everything that was planned to happen during
this update period did happen on the planned dates.
b. If the project manager chooses Schedule Change, he or she must submit a
Schedule Update Form (see Figure 7.12) for the project. The form lists all
project activities, with a Start Date column, an “A” column, a blank Start
Date Change column, and similar columns for the end date. If an activity
started, the project manager writes an A , indicating an actual date, next
to the start date. If the actual start date differs from the planned date, the
project manager writes the updated start date in the Start Date Change col-
umn. If a future start date is changed (say, postponed for 2 months), the new
start date is written in the Start Date Change column without writing an A
Schedule Update Form
Data Date: 3/15/2003
PM ignature:
Date:
Schedule Signature:
Date:
PM: John Doe
Project No.: FGH2133
Project Name: Office Building, downtown Tampa
Start Date
End Date Orig. Rem.
%
Activity name
Start Date A
Change
End Date
A
Change
Dur.
Dur.
Comp.
1
NTP
1/3/2003 A
0
0
100%
2
Mobilize
1/6/2003 A
1/8/2003 A
3
0
100%
11 a
3
Dewatering
1/9/2003 A
1/19/2003 A
0
100%
4
Excavation—North Side
1/20/2003 A
1/29/2003 A
9
0
100%
5
Excavation—South Side
2/3/2003 A
2/25/2003 A
10
0
100%
6
Drill Piles—North Side
1/30/2003 A
2/28/2003 A
13
0
100%
7
Drill Piles—South Side
3/3/2003 A
3/19/2003
13
3
77%
8
Concrete Piles —North Side
3/3/2003 A
3/11/2003 A
7
0
100%
9
Concrete Piles —SouthSide 3/20/2003
3/28/2003
7
7
0%
10 Pile Caps—North Side
3/12/2003 A
3/28/2003
13
10
23%
11 Pile Caps—South Side
3/31/2003
4/16/2003
13
13
0%
12 Footings—North Side
3/24/2003
4/4/2003
10
10
0%
13 Footings—South Side
4/7/2003
4/22/2003
12
12
0%
14 Elevator Pit —North Side
3/31/2003
4/9/2003
8
8
0%
15 Elevator Pit —SouthSide
4/14/2003
4/23/2003
8
8
0%
a This activity is on a 7-day per week calendar.
Figure 7.12 Sample Schedule Update Form
Search WWH ::




Custom Search