Civil Engineering Reference
In-Depth Information
15.
Repeat exercise 12 using contiguous activities.
16.
Prove that using interruptible activities in the following project allows the project
to finish 5 days earlier than if the activities were contiguous.
Type Rel
a
Activity
Duration
IPA
g S F
S F
F
FF
A
7
-
B
6
A
SS
3
A
FF
4
C
2
B
SS
1
B
FF
D
6
C
SS
C
FF
4
E
10
D
SS
3
D
FF
2
a
If the relationship type is not mentioned, it is finish to start (FS). If no lag is mentioned, it is zero.
17.
Give real-life (not necessarily construction) examples for the following:
a.
An SS (start-to-start) relationship without lag. No FF (finish-to-finish) rela-
tionship is required.
b.
An SS relationship with lag. No FF relationship is required.
c.
An SS and FF combination relationship
d.
An FF relationship, with or without lag
18.
A subcontractor must do the following:
a.
Framing (5 days)
b.
Drywall installation (4 days)
c.
Drywall finish and paint (3 days)
Assuming he wants to make sure each activity finishes as least 1 day after its
predecessor has finished, draw these three activities in a precedence diagram
and calculate how much time the subcontractor would need to finish all three
activities.
19.
Look at your solution to the previous exercise. Is it a unique solution, or can you
achieve the same result with different logic?
20.
Give an example for each of the following:
a.
Start-restricted float
b.
Finish-restricted float
c.
Double-restricted float
d.
Unrestricted float
Search WWH ::
Custom Search