Civil Engineering Reference
In-Depth Information
8. Define a fast-track operation . Briefly discuss its pros and cons.
9. Mention examples in which using fast-tracking is bad, good, or a “must” option.
10. From the following table, draw the precedence network, perform the CPM
calculations, and complete the table entries, assuming interruptible activities.
Type Rel a
Activity
Duration
IPA
g S F
S F
F
FF
A
3
-
B
5
A
SS
3
C
2
A
D
6
B
FF
C
a If the relationship type is not mentioned, it is finish to start (FS). If no lag is mentioned, it is zero.
11. From the following table, draw the precedence network, perform the CPM
calculations, and complete the table entries, assuming interruptible activities.
Type Rel a
Activity
Duration
IPA
g S F
S F
F
FF
A
4
-
B
3
-
C
8
A
SF
D
7
A, B
E
6
D
SS
3
F
3
D
G
5
F
SS
2
F
FF
a If the relationship type is not mentioned, it is finish to start (FS). If no lag is mentioned, it is zero.
12. From the following table, draw the precedence network, perform the CPM
calculations, and complete the table entries, assuming interruptible activities.
Type Rel a
Activity
Duration
IPA
g S F
S F
F
FF
A
5
-
B
7
A
SS
2
C
8
A
D
10
A
SS
3
FF
E
4
B
FF
2
F
6
C, D
G
2
E, F
a If the relationship type is not mentioned, it is finish to start (FS). If no lag is mentioned, it is zero.
13. Repeat exercise 10 using contiguous activities.
14. Repeat exercise 11 using contiguous activities.
 
Search WWH ::




Custom Search