Civil Engineering Reference
In-Depth Information
Example 5.1
Perform the CPM calculations for the network shown in Figure 5.22.
Solution
Forward Pass
1. Start the project at activity A. ES = 0. EF = 0 + 2 = 2.
2. Activity B can start as soon as activity A is finished. ES = 2. EF = 2 +
6 = 8.
3. Activity C can start 1 day after A has started. ES = 1, EF = 1 + 11 =
12.
4. Activity D can start 2 days after activity B has started. ES = 2 + 2 =
4. Use the later of EF = 4 + 7 = 11 and the EF (for B) = 8. We choose
EF = 11.
5. Activity E can start as soon as B is finished. ES = 8. Use the later of
EF = 8 + 4 = 12 and EF (for C) + 5-day lag = 12 + 5 = 17. We choose
EF = 17.
6. Activity F has no restriction for its start (dangling activity). ES = 0, EF
= 0 + 8 = 8.
7. Activity G can start after both D and E are finished. ES (for G) = 17 (the
later of 11 and 17). Use the later of EF = 17 + 3 = 20 and EF (for F)
+ 4-day lag = 8 + 4 = 12. We choose EF = 20.
8. The calculated early finish date for the project is day 20 (project dura-
tion is 20 days).
Solution
The Backward Pass
1. StartatactivityG. LF = 20, LS = 20 3 = 17.
2. Activity F must finish 4 days prior to the finish of G (i.e., LF = 20 4
= 16; LS = 16 8 = 8).
3. Activity E must finish before G can start. LF = 17. LS = 17 4 = 13.
4. Activity D must finish before G can start. LF = 17. LS = 17 7 = 10.
5. Activity C must finish 5 days before the finish of E. LF = 17 5 = 12.
LS = 12 11 = 1.
6. Activity B must finish before D has finished, on day 17, and before
E has started, on day 13. LF = 13 (the earlier). Use the earlier of
LS = LF Dur = 13 6 = 7 and 2 days before the LS for D (i.e., 8).
We choose the earlier: LS = 7.
 
Search WWH ::




Custom Search