10.
For the following schedule, draw the node network, perform the CPM calcula-
tions, mark the critical path, and complete the table.
Activity
Duration
IPA
Lag
ES
EF
LS
LF
TF
FF
A
5
-
B
6
A
C
4
A
3
D
5
A
E
3
B
F
2
C, B
11.
For the following schedule, draw the node network, perform the CPM calcula-
tions, mark the critical path, and complete the table.
Activity
Duration
IPA
Lag
ES
EF
LS
LF
TF
FF
A
4
-
B
9
-
C
6
A
D
4
A
B
2
E
4
B
F
2
B, C
G
6
D
E
3
H
3
F, G
12.
For the following schedule, draw the node network, perform the CPM calcula-
tions, mark the critical path, and complete the table.
Activity
Duration
IPA
Lag
ES
EF
LS
LF
TF
FF
A
5
-
B
6
A
C
4
A
3
D
5
A
E
9
B
F
7
B
2
C
G
6
C
H
8
C
D
4
I
3
D
J
7
E, G
F
2
K
4
F, G, H
L
1
H
3
I
M
2
K, L